Multiple Choice
A finish to start lag delay is usually shown:
A) As an added value in the predecessor's activity time.
B) On the line adjoining the two activity nodes.
C) As an added value in the predecessors early start time.
D) As a subtracted value in the follower's early finish time.
Correct Answer:

Verified
Correct Answer:
Verified