menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management
  4. Exam
    Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain
  5. Question
    A Project Consists of Four Activities with Information as Shown
Solved

A Project Consists of Four Activities with Information as Shown

Question 87

Question 87

Multiple Choice

A project consists of four activities with information as shown in the table.What is the overall variance of the project's duration? A project consists of four activities with information as shown in the table.What is the overall variance of the project's duration?   A)  13 B)  17 C)  26 D)  35


A) 13
B) 17
C) 26
D) 35

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q1: A key element of extreme programming is:<br>A)Frequent

Q47: Which of these numerical (quantity)comparisons is CORRECT?<br>A)Scrum

Q66: Once the organization elevates its constraint,its system

Q85: A project consists of four activities

Q86: A project is represented by the

Q90: The waterfall project development process is well-suited

Q91: A project is represented by the

Q97: A product backlog is the final list

Q100: CCPM advocates performing all non-critical activities:<br>A)As late

Q104: What are some arguments against the XP

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines