Multiple Choice
The waterfall project development process is well-suited for instances where:
A) Requirements are allowed to float throughout the duration of the project.
B) Customer needs change quickly.
C) Time constraints exist.
D) Budget constraints exist.
Correct Answer:

Verified
Correct Answer:
Verified