Solved

A Project Is Represented by the Activity Durations (In Days,estimated

Question 91

Multiple Choice

A project is represented by the activity durations (in days,estimated at 90% likelihood of completion) and precedence requirements shown in the table.How many feeder buffers are needed if this project is managed using critical chain methodology?  Activity  Predecessor  Length  Activity  Predecessor  Length  A 18 E  C, D 13 B 16 F  C 9 C  A 22 G  E, F 15 D  B 14\begin{array} { | l | l | l | l | l | l | } \hline \text { Activity } & \text { Predecessor } & \text { Length } & \text { Activity } & \text { Predecessor } & \text { Length } \\\hline \text { A } & - & 18 & \text { E } & \text { C, D } & 13 \\\hline \text { B } & - & 16 & \text { F } & \text { C } & 9 \\\hline \text { C } & \text { A } & 22 & \text { G } & \text { E, F } & 15 \\\hline \text { D } & \text { B } & 14 & & & \\\hline\end{array}


A) 0
B) 1
C) 2
D) 3

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions