Multiple Choice
A project is represented by the activity durations (in days,estimated at 90% likelihood of completion) and precedence requirements shown in the table.How many feeder buffers are needed if this project is managed using critical chain methodology?
A) 0
B) 1
C) 2
D) 3
Correct Answer:

Verified
Correct Answer:
Verified
Q10: The buffers supplied to non-critical paths in
Q47: Which of these numerical (quantity)comparisons is CORRECT?<br>A)Scrum
Q50: Your next project consists of 8 consecutive
Q83: The critical chain is usually the same
Q86: A project is represented by the
Q87: A project consists of four activities with
Q90: The waterfall project development process is well-suited
Q96: What is Agile PM and what makes
Q97: A product backlog is the final list
Q100: CCPM advocates performing all non-critical activities:<br>A)As late