Multiple Choice
The BEST method for establishing the existence of resource conflicts across project activities uses:
A) Gantt charts.
B) Network diagrams.
C) Pareto diagrams.
D) Resource loading charts.
Correct Answer:

Verified
Correct Answer:
Verified