Multiple Choice
In general,when constructing a resource loading chart,one should avoid:
A) Splitting the activities.
B) Obeying the pre-established precedence requirements for the activities.
C) Identifying the slack for each activity.
D) Changing the duration of the activities.
Correct Answer: