Multiple Choice
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day) to this project with work taking place on a 5-day-per-week basis.If the project manager is told that the total number of hours per week cannot exceed 48,what is the first week that some resource leveling must occur?
A) Week 2
B) Week 6
C) Week 4
D) Week 5