Create a Resource Loading Table and Perform Resource Leveling on the Project

Question 90

Essay

Create a resource loading table and perform resource leveling on the project composed of the activities in this table.Activities listed in the table are measured in the number of eight-hour days.The maximum amount of time used per day is 16 hours.
 Activity  Time  Predecessor A6B1C2 A, B D4E1C,DF1EG6EH4 FT4 FK3G,HL5 J, KM3 L\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \mathrm { A } & 6 & - \\\hline \mathrm { B } & 1 & - \\\hline \mathrm { C } & 2 & \text { A, B } \\\hline \mathrm { D } & 4 & - \\\hline \mathrm { E } & 1 & \mathrm { C } , \mathrm { D } \\\hline \mathrm { F } & 1 & \mathrm { E } \\\hline \mathrm { G } & 6 & \mathrm { E } \\\hline \mathrm { H } & 4 & \mathrm {~F} \\\hline \mathrm { T } & 4 & \mathrm {~F} \\\hline \mathrm { K } & 3 & \mathrm { G } , \mathrm { H } \\\mathrm { L } & 5 & \mathrm {~J} , \mathrm {~K} \\\hline \mathrm { M } & 3 & \mathrm {~L} \\\hline\end{array}

Correct Answer:

verifed

Verified

The initial resource loading table with ...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions