Multiple Choice
A project consists of eleven activities (all times are given in days) and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What day does activity H start under a leveled project with the four worker limitation?
A) Day 27
B) Day 28
C) Day 29
D) Day 30
Correct Answer:

Verified
Correct Answer:
Verified