Multiple Choice
A project consisting of six activities is represented in the resource loading table shown below.There is a limit of 12 hours' time spent on this project for any given day.Which activity should be left alone if at all possible in the adjustment process among the candidates?
A) Activity B
B) Activity C
C) Activity F
D) Activity E
Correct Answer:

Verified
Correct Answer:
Verified