Use the Data to Calculate the Earned Value for the Project.All

Question 65

Multiple Choice

Use the data to calculate the earned value for the project.All amounts are in thousands of dollars.  Duration (weeks)  510152025% Comp  Conceptual Design 106100% Graphics Design 1264100% Copyright 45625% Samples 4230% Tooling 69410% Production 26145% Total 1018222624 Cumulative 10285076100\begin{array} { | l | l | l | l | l | l | l | } \hline &{ \text { Duration (weeks) } } & \\\hline & 5 & 10 & 15 & 20 & 25 & \% \text { Comp } \\\hline \text { Conceptual Design } & 10 & 6 & & & & 100 \% \\\hline \text { Graphics Design } & & 12 & 6 & 4 & & 100 \% \\\hline \text { Copyright } & & & 4 & 5 & 6 & 25 \% \\\hline \text { Samples } & & & 4 & 2 & & 30 \% \\\hline \text { Tooling } & & & 6 & 9 & 4 & 10 \% \\\hline \text { Production } & & & 2 & 6 & 14 & 5 \% \\\hline \text { Total } & 10 & 18 & 22 & 26 & 24 & \\\hline \text { Cumulative } & 10 & 28 & 50 & 76 & 100 & \\\hline\end{array}


A) $38,500
B) $46,550
C) $56,750
D) $61,125

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions