Multiple Choice
Which of the following is incorrect regarding time/cost trade-offs?
A) The relationship between time and cost is proportional
B) Some activities cannot be crashed
C) The minimum cost can be found by crashing all activities as much as possible
D) Crashing priority is based on the amount of uncertainty in activity times