    Define Critical Path and Explain How It Is Identified Once
Solved

Define Critical Path and Explain How It Is Identified Once

Question 98

Question 98

Essay

Define critical path and explain how it is identified once a project schedule is calculated.

Correct Answer:

verifed

Verified

The Critical Path (CP) is the longest pa...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q93: When the beta probability distribution is used

Q94: In most organizations, projects cut across organizational

Q95: A project has three parallel paths. A-B-C

Q96: List at least six principal factors (contributors)

Q97: Rose is in charge of the

Q99: Crash time is the longest possible time

Q100: Which one of the following is NOT

Q101: Which one of the following statements about

Q102: Shea is in charge of the

Q103: You are responsible for managing a

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines