Essay
A company wants to develop a project using PERT to modify one of their products which has poor sales. They have determined the following activities, precedence relationships and time estimates in days for the project:
a. What is the expected duration for activity a?
b. What is the variance for activity d?
c. How many paths are there in the network?
d. What is the earliest start ES) time for activity e?
e. What is the slack in days for activity b?f. What is the critical path
g. What is the duration of the critical path in days
h. What is the standard deviation of the critical path
i. What is the probability that the project will take longer than 28 weeks to complete?
Correct Answer:

Answered by ExamLex AI
Correct Answer:
Answered by ExamLex AI
Q7: The following network shows all the
Q11: A manufacturing company is planning to
Q22: Explain the role of the project managers
Q42: Define a project. Give some non-manufacturing or
Q46: Which of the following is not considered
Q55: In which stage in the project life
Q59: A statement of work would be developed
Q69: Strong leadership is an impediment to project
Q85: A slack of 2 means the project
Q96: List at least six principal factors (contributors)