Multiple Choice
A standard procedure for numerically measuring a project's progress is referred to as a(n)
A) program evaluation and review technique (PERT) .
B) critical path method (CPM) .
C) Gantt chart.
D) earned value analysis.
Correct Answer:

Verified
Correct Answer:
Verified