Multiple Choice
A bar graph displaying when activities are scheduled to start,when they will be finished,and where extra time is available is known as a
A) PERT chart.
B) work breakdown structure (WBS) .
C) Gantt chart.
D) responsibility assignment matrix (RAM) .
Correct Answer:

Verified
Correct Answer:
Verified