Multiple Choice
Which of the following statements is generally true regarding the relationship between project crashing costs and indirect costs?
A) both crashing costs and indirect costs are highest when the project is shortened
B) only indirect costs increase when the project is shortened
C) both are unaffected by the length of the project
D) crashing costs increase when the project is shortened while indirect costs decrease when the project is shortened
Correct Answer:

Verified
Correct Answer:
Verified
Q58: A project consists of the following activities:<br>
Q59: Slack represents the amount of time an
Q60: A project consists of the following four
Q61: The following table of probabilistic time estimates
Q62: In general,the earliest finish time for an
Q64: One disadvantage of Gantt charts,especially for large
Q65: Issues of cultural diversity in project management
Q66: The estimated variance for an activity with
Q67: Control,one of the basic elements of a
Q68: The three primary elements of project management