Multiple Choice
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
Table 9.2
-Using Table 9.2,the expected time to complete the project is
A) 34.17 weeks.
B) 33.23 weeks.
C) 31.00 weeks.
D) 21.67 weeks.
Correct Answer:

Verified
Correct Answer:
Verified
Q13: A project consists of the following activities:<br>
Q13: For activities on a project's critical path,<br>A)earliest
Q15: The following table of probabilistic time estimates
Q16: A project consists of the following activities:<br>
Q17: In general,projects are subject to less uncertainty
Q18: A project consists of the following activities:<br>
Q20: A project consists of the following four
Q22: Which of the following is the universal
Q24: A project's duration can be reduced by
Q64: One disadvantage of Gantt charts,especially for large