Multiple Choice
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
Table 9.2
-Using Table 9.2,the variance for activity E is
A) 1.291.
B) 1.667.
C) 2.582.
D) 2.778.