    The Following Table of Probabilistic Time Estimates (In Weeks)and Activity
Solved

The Following Table of Probabilistic Time Estimates (In Weeks)and Activity

Question 41

Question 41

Multiple Choice

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.    Table 9.2 -Using Table 9.2,the variance for activity E is A) 1.291. B) 1.667. C) 2.582. D) 2.778.
Table 9.2
-Using Table 9.2,the variance for activity E is


A) 1.291.
B) 1.667.
C) 2.582.
D) 2.778.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q16: The estimated mean time for an activity

Q19: Why have projects taken on a more

Q37: CPM/PERT The key elements of project control

Q40: With an activity-on-node (AON)network diagram,the nodes indicate

Q42: The following table of probabilistic time estimates

Q45: In general,crashing costs decrease as a project's

Q46: The critical path is the shortest path

Q75: In project management the term slack refers

Q83: For an activity-on-node (AON)network,<br>A)arrows represent activities and

Q92: Managing quality is not an important part

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines