The Following Table of Probabilistic Time Estimates (In Weeks)and Activity

Question 42

Multiple Choice

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.    Table 9.2 -Using Table 9.2,the probability that the project could be completed in 34 weeks or less is approximately A) 0.86. B) 0.89. C) 0.91. D) 0.96.
Table 9.2
-Using Table 9.2,the probability that the project could be completed in 34 weeks or less is approximately


A) 0.86.
B) 0.89.
C) 0.91.
D) 0.96.