Multiple Choice
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
Table 9.2
-Using Table 9.2,the probability that the project could be completed in 34 weeks or less is approximately
A) 0.86.
B) 0.89.
C) 0.91.
D) 0.96.
Correct Answer:

Verified
Correct Answer:
Verified
Q19: Why have projects taken on a more
Q37: CPM/PERT The key elements of project control
Q40: With an activity-on-node (AON)network diagram,the nodes indicate
Q41: The following table of probabilistic time estimates
Q45: In general,crashing costs decrease as a project's
Q46: The critical path is the shortest path
Q47: The estimated variance for an activity with
Q75: In project management the term slack refers
Q83: For an activity-on-node (AON)network,<br>A)arrows represent activities and
Q92: Managing quality is not an important part