Multiple Choice
Standard subnetworks should be developed for those portions of projects for which
A) repeat once or twice in the project.
B) the logical relationships among the activities have been well established through historical practice.
C) need to be fast tracked to get the project scheduled.
D) take up too much space on the network diagram.
Correct Answer:

Verified
Correct Answer:
Verified