Multiple Choice
Earliest finish time (EF) is the earliest time by which a specific activity can be completed, calculated
A) by subtracting the activity's estimated duration from the earliest finish time of the activity's predecessor: EF = EF predecessor - Estimated Duration.
B) by subtracting the activity's estimated duration to the activity's earliest start time: EF = ES - Estimated Duration.
C) by adding the activity's estimated duration to the earliest start time of the activity's succeeding activity: EF = ES succeeding activity + Estimated Duration.
D) by adding the activity's estimated duration to the activity's earliest start time: EF = ES + Estimated Duration.
Correct Answer:

Verified
Correct Answer:
Verified
Q102: The amount of slack should determine the
Q103: The estimated duration for each activity is
Q104: For large projects that involve several hundred
Q105: Total slack for the project is the
Q106: Calculate the earliest start for Task B
Q108: The total completion time is 25 days.Task
Q109: The estimated resources required for an activity
Q110: Free slack of an activity is<br>A) the
Q111: The project control process must occur regularly
Q112: At the beginning of every project, it