When Evaluating Work Packages That Have a Negative Cost Variance

Question 7

Multiple Choice

When evaluating work packages that have a negative cost variance, you should focus on taking corrective actions to reduce the costs of:


A) activities that have a small cost estimate.
B) activities that have a moderate cost estimate.
C) activities that have a large cost estimate.
D) all the activities in the project.

Correct Answer: