Multiple Choice
Estimates in the earliest stages of project selection are usually made using estimates based from previous projects that can be _____-multiplied by an adjustment factor to make the new estimate proportional to the original.
A) aggregated
B) subtotaled
C) scaled
D) predefined
E) rolled up
Correct Answer:

Verified
Correct Answer:
Verified