Estimates in the Earliest Stages of Project Selection Are Usually

Question 38

Multiple Choice

Estimates in the earliest stages of project selection are usually made using estimates based from previous projects that can be _____-multiplied by an adjustment factor to make the new estimate proportional to the original.


A) aggregated
B) subtotaled
C) scaled
D) predefined
E) rolled up