    Exam 9: Estimating and Managing Costs
  5. Question
    _____ Are Measurable Factors That Can Be Used in an Equation
Solved

_____ Are Measurable Factors That Can Be Used in an Equation

Question 33

Question 33

Multiple Choice

_____ are measurable factors that can be used in an equation to calculate a result.


A) Humm factors
B) Free floats
C) Attributes
D) RFPs
E) Parameters

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q28: In estimating costs to compare and select

Q29: To calculate the ETC, the manager must

Q30: If services or products will be provided

Q31: Cost variance CV) is _.<br>A) earned value

Q32: To calculate the EAC, the estimate to

Q34: If the cost estimates by vendors are

Q35: Jean is managing a project in his

Q36: Contractual agreements with vendors always require full

Q37: Earned value management allows for partial completion

Q38: Estimates in the earliest stages of project

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines