Multiple Choice
Jean is managing a project in his organization. The planned value for this project is $4,500. At the end of eight weeks, he finds that his earned value is $3,500. What is the present schedule variance for the project? What does the variance signify?
A) $-1,000; behind schedule
B) $+1,000; ahead of schedule
C) $-1,000; on schedule
D) $+1,000; on schedule
E) $+1,000; behind schedule
Correct Answer:

Verified
Correct Answer:
Verified
Q30: If services or products will be provided
Q31: Cost variance CV) is _.<br>A) earned value
Q32: To calculate the EAC, the estimate to
Q33: _ are measurable factors that can be
Q34: If the cost estimates by vendors are
Q36: Contractual agreements with vendors always require full
Q37: Earned value management allows for partial completion
Q38: Estimates in the earliest stages of project
Q39: The difference between the earned value and
Q40: During the project, the manager can evaluate