Multiple Choice
Which of the following is true about management reserves versus contingency reserves?
A) Contingency reserves are not likely to be spent.
B) Management reserves are not part of the project's budget baseline.
C) Management reserves are not included in the total project budget.
D) Management reserves are likely to be spent.
E) Contingency reserves are not part of the total budget for the project.
Correct Answer:

Verified
Correct Answer:
Verified
Q20: The detailed cost estimates for each activity
Q21: The schedule variance is the difference between
Q22: If a project consists of activities that
Q23: _ is the budget for the entire
Q24: At the end of three months, the
Q26: Estimates that are calculated by multiplying measured
Q27: The project manager prefers to keep the
Q28: In estimating costs to compare and select
Q29: To calculate the ETC, the manager must
Q30: If services or products will be provided