Multiple Choice
In estimating costs to compare and select projects, which of the following is true
A) Social factors are the most important consideration when choosing between competing projects.
B) The methods used to estimate the cost of the project during the selection phase are slower than those used to create detailed estimates in later phases.
C) The amount of time and resources used to make estimates should be appropriate primarily to the location of the project.
D) Estimates in the earliest stages of project selection are usually made using estimates based from previous projects.
E) Experienced managers can make accurate estimates only with more detailed information.
Correct Answer:

Verified
Correct Answer:
Verified
Q23: _ is the budget for the entire
Q24: At the end of three months, the
Q25: Which of the following is true about
Q26: Estimates that are calculated by multiplying measured
Q27: The project manager prefers to keep the
Q29: To calculate the ETC, the manager must
Q30: If services or products will be provided
Q31: Cost variance CV) is _.<br>A) earned value
Q32: To calculate the EAC, the estimate to
Q33: _ are measurable factors that can be