Multiple Choice
At the end of three months, the cost factors in A&B's healthcare project are as follows: Earned value = $17,000, Actual cost = $18,200. What is the cost variance CV) and cost performance index CPI) for the project?
A) $+1,200; 1.07
B) $-1,200; 0.93
C) $-1,200; 1.07
D) $+35,200; 0.93
E) $+35,200; 1.07
Correct Answer: