Multiple Choice
If the appropriate scheduling equation for task A of a project were W = D * U,and it was initialized so that W = 40d,D = 10d,and U = 4 resources,and task A is an effort-driven activity,correctly balance this equation if the value for U is changed from 4 to 5.To balance the equation,the altered variable and its new value are __________.
A) D = 6w
B) W = 6d
C) D = 8d
D) W = 6d.