Multiple Choice
Given a scheduling equation W = D * U,if the equation for task J is initialized so that W = 20d,D= 5d,and U = 4 resources,and task J is a non-effort-driven activity (where D is held constant when resources are changed) ,correctly balance this equation if the value for U is changed from 4 to 5.To balance the equation,the altered variable and its new value are __________.
A) D = 25w
B) W = 25d
C) D = 80w
D) W = 8d
Correct Answer:

Verified
Correct Answer:
Verified