Multiple Choice
During initial project planning,activities are identified and sorted.In completing this process,each level in the hierarchy should limit the number of activities to a range between __________.
A) 5 to 10 activities
B) 0 to 5 activities
C) 2 to 20 activities
D) 10 to 20 activities
Correct Answer:

Verified
Correct Answer:
Verified