Under the Precedence Diagramming Method,the situation which occurs when two activities can start at different times,have different durations,but are planned to be competed at the same time is called:
A) Finish-To-Start FS)
B) Start-To-Start SS)
C) Finish-To-Finish FF)
D) Start-To-Finish SF)