Question 7

Multiple Choice

Under the Precedence Diagramming Method,the situation which occurs when two activities can start at different times,have different durations,but are planned to be competed at the same time is called:


A) Finish-To-Start FS)
B) Start-To-Start SS)
C) Finish-To-Finish FF)
D) Start-To-Finish SF)
E) none of the above

Correct Answer: