Multiple Choice
Waiting to leave your shift until another person shows up is an example of:
A) Finish-To-Start FS)
B) Start-To-Start SS)
C) Finish-To-Finish FF)
D) Start-To-Finish SF)
E) none of the above
Correct Answer:

Verified
Correct Answer:
Verified