Multiple Choice
SPC uses two control charts to ensure quality in manufacturing: the sample mean (X-bar) chart and the sample range (R) chart. The control chart limits are established for X-bar and R charts based upon tolerances set during the design stage of the product. In most cases, problems are ________________ before any ___________ parts are produced, thus reducing scrap and rework.
A) diagnosed and resolved / substandard
B) identified / faulty
C) solved / defective
D) identified / new
E) fixed / defective
Correct Answer:

Verified
Correct Answer:
Verified
Q3: The new or modified part agreement between
Q4: Implementing TQM requires the following:efining the _.Identifying
Q5: Customer focus and satisfaction
Q6: Six-sigma suppliers focus on all of the
Q7: The most severe penalty for poor quality
Q9: lthough the basic ideas of TM are
Q10: _ standards can be applied to both
Q11: Intensive price competition and information technology have
Q12: The _ suppliers usually get the long-run
Q13: Implementing TQM also requires the following: Negotiating