Multiple Choice
The main difference between CPM and PERT is
A) CPM and PERT use different activity time estimates.
B) PERT analysis is less expensive to conduct.
C) PERT lends itself to computerization while CPM networks must be constructed manually.
D) CPM integrates time and cost performance while PERT is based solely on time performance.
Correct Answer:

Verified