Question 81
Multiple Choice
Micah is a fairly new project manager.He estimated for a project plan (on the planning phase) that the project would cost $50,000 and take 20 weeks.According to the margin of error guidelines for well-done estimates,that could range from:
Question 82
True/False
A classic planning mistake mentioned in the textbook is motivating employees with financial rewards instead of recognition and genuine thanks.
Question 83
Multiple Choice
Which would generally NOT be taken into consideration for project portfolio management in an organization?
Question 84
Essay
What can you do to manage scope creep?
Question 85
Multiple Choice
System prototyping is BEST characterized as:
Question 86
Multiple Choice
If the skills required by a project cannot be met by the available project team,which would probably NOT be a reasonable solution?
Question 87
True/False
Scope creep is when new requirements are added to the project after the original project scope was defined and 'frozen'.
Question 88
True/False
Extreme Programming (XP)stresses customer satisfaction and teamwork.
Question 89
True/False
Throwaway Prototyping balances the benefits of well-thought-out analysis and design phases with the advantages of using prototypes to refine key issues before a system is built.
Question 90
Multiple Choice
Tatiana is developing a staffing plan for a project.Which of the following would she NOT consider in developing such a staffing plan?
Question 91
True/False
Using industry standards,the general estimated project time for the Implementation phase is 15%.
Question 92
True/False
If you had a project with very clear requirements;familiar technologies;not super complex;reliable;a very long time schedule and where the need for schedule visibility is low - the best methodology might be Extreme programming