 Activity  Immediate  Predecessor(s)   Most  Optimistic  Most  Likely  Most  Pessimistic  A 1123 B  A 2412 C  A 123 D  B 678 E  B,C 101214 F  D 234 G  E,F 1515 H  A 2514\begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array} { c } \text { Most } \\\text { Optimistic }\end{array} & \begin{array} { c } \text { Most } \\\text { Likely }\end{array} & \begin{array} { c } \text { Most } \\\text { Pessimistic }\end{array} \\\hline \text { A } & - 1 & 1 & 2 & 3 \\\text { B } & \text { A } & 2 & 4 & 12 \\\text { C } & \text { A } & 1 & 2 & 3 \\\text { D } & \text { B } & 6 & 7 & 8 \\\text { E } & \text { B,C } & 10 & 12 & 14 \\\text { F } & \text { D } & 2 & 3 & 4 \\& & & & \\\text { G } & \text { E,F } & 1 & 5 & 15 \\\text { H } & \text { A } & 2 & 5 & 14 \\\hline\end{array}
-Using Table 3.1,what is the earliest expected time of completion of the whole project?


A) less than or equal to 19 weeks
B) greater than 19 but less than or equal to 21 weeks
C) greater than 21 but less than or equal to 24 weeks
D) greater than 24 weeks

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions