Multiple Choice
Table 3.6
-Using Table 3.6,what is the earliest completion time of the project?
A) less than or equal to 25 weeks
B) greater than 25 weeks but less than or equal to 30 weeks
C) greater than 30 weeks but less than or equal to 35 weeks
D) greater than 35 weeks
Correct Answer:

Verified
Correct Answer:
Verified