Table 36 -Using Table 3

Question 42

Multiple Choice

Table 3.6
 Activity  Immediate  Predecessor(s)   Time  (weeks)   A 3 B 9 C 10 D  A 4 E  B 12 F  C 5 G  B,D 6 H  E,F 7 I  H 8\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array} { c } \text { Time } \\\text { (weeks) }\end{array} \\\hline \text { A } & \cdots & 3 \\\text { B } & \cdots & 9 \\\text { C } & \cdots & 10 \\\\\text { D } & \text { A } & 4 \\\text { E } & \text { B } & 12 \\\text { F } & \text { C } & 5 \\\\\text { G } & \text { B,D } & 6 \\\text { H } & \text { E,F } & 7 \\\text { I } & \text { H } & 8 \\\hline\end{array}
-Using Table 3.6,what is the earliest completion time of the project?


A) less than or equal to 25 weeks
B) greater than 25 weeks but less than or equal to 30 weeks
C) greater than 30 weeks but less than or equal to 35 weeks
D) greater than 35 weeks

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions