Which of the following statements about MRP and MPS are TRUE?


A) MPS calculates requirements for all the levels of the BOM.
B) MRP calculates requirements only for the first-level items in the BOM.
C) Both MRP and MPS calculate requirements based on historical data only.
D) MRP calculates requirements for all levels of the BOM.
E) MPS calculates requirements only for the first-level items in the BOM.