Multiple Choice
Which of the following statements about consumption-based planning is TRUE?
A) Planning is based on historical data.
B) Planning is based on exploding the BOM.
C) Dependent demand is derived from independent demand.
D) It is used for high-value materials
E) Planning is based on MPS.
Correct Answer:

Verified
Correct Answer:
Verified
Q13: Consider the following scenario,then choose which one
Q14: Which of the following statements about MRP
Q15: A company has two options for procuring
Q16: MPS is generally appropriate for high-value items
Q17: Which of the following options represents categories
Q19: Which of the following is most likely
Q20: In SAP ERP production planning strategy,net requirements
Q21: Which of the following are steps in
Q22: MRP data are specific to each plant.
Q23: Master production scheduling is specialized form of<br>A)MRP.<br>B)Demand