Multiple Choice
A company has two options for procuring materials: make or buy.Which MRP data view of the material master will the ERP system consider for this decision?
A) MRP 1
B) MRP 2
C) MRP 3
D) MRP 4
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified