Project managers must manage the __________, which consists of tasks that must start and finish on schedule or the project will be delayed unless corrective action is taken.
A) Over allocation
B) Critical path
C) Triple constraints
D) Scope creep
Correct Answer:

Verified
Correct Answer:
Verified