Multiple Choice
In a BIP problem, 1 corresponds to a yes decision and 0 to a no decision. If there are 4 projects under consideration (A, B, C, and D ) and at most 2 can be chosen then the following constraint needs to be added to the formulation:
A) A + B + C + D ≤ 1.
B) A + B + C + D ≤ 2.
C) A + B + C + D ≤ 4.
D) A + B + C + D = 2.