A firm has prepared the following binary integer program to evaluate a number of potential new capital projects. The firm's goal is to maximize the net present value of their decision while not spending more than their currently available capital.
Max 100x1 + 120x2 + 90x3 + 135x4
s.t. 150x1 + 200x2 + 225x3 + 175x4 ? 500 {Constraint 1}
X1 + x2 + x3 + x4 ? 2 {Constraint 2}
X2 + x4 ? 1 {Constraint 3}
X2 + x3 ? 1 {Constraint 4}
X1 = x4 {Constraint 5}
Set up the problem in Excel and find the optimal solution. Which projects are selected?
A) Project 1
B) Project 2
C) Project 4
D) Projects 2 and 3
E) Projects 1 and 3
Correct Answer:

Verified
Correct Answer:
Verified
Q35: Variables whose only possible values are 0
Q36: A firm has prepared the following
Q37: The Excel sensitivity report can be used
Q38: Note: This problem requires the use
Q39: In a BIP problem, 1 corresponds to
Q41: Note: This problem requires the use
Q42: A firm has prepared the following
Q43: Note: This problem requires the use
Q44: BIP can be used to determine the
Q45: In a BIP problem, 1 corresponds to