Question 41

Multiple Choice

Note: This problem requires the use of a linear programming application such as Solver or Analytic Solver.
Your employer is trying to select from a list of possible capital projects. The projects, along with their cost and benefits, are listed below. The capital budget available is $1 million. In addition to spending constraints, your employer would like to select at least two projects. If project 1 is chosen then project 2 cannot be selected. Formulate the problem as a linear program and determine the optimal solution.
 Project  Cost  Net Presert Value  Notes 1$250,000$500,000 Carrnot be selected if 2 is selected 2$500,000$750,000 Carrot be selected if 1 is selected 3$290,000$333,0004$650,000$400,0005$750,000$600,000\begin{array} { c c c c } \text { Project } & \text { Cost } & \text { Net Presert Value } & \text { Notes } \\1 & \$ 250,000 & \$ 500,000 & \text { Carrnot be selected if } 2 \text { is selected } \\2 & \$ 500,000 & \$ 750,000 & \text { Carrot be selected if } 1 \text { is selected } \\3 & \$ 290,000 & \$ 333,000 & \\4 & \$ 650,000 & \$ 400,000 & \\5 & \$ 750,000 & \$ 600,000 &\end{array}


A) Project 1 and project 2
B) Project 1 and project 3
C) Project 1 and project 5
D) Project 2 and project 3
E) Project 3 and project 5