Perth Mining Company operates two mines for the purpose of extracting gold and silver. The Saddle Mine costs $14,000/day to operate, and it yields 50 oz of gold and 3,000 oz of silver each day. The Horseshoe Mine costs $16,000/day to operate, and it yields 75 oz of gold and 1,000 oz of silver each day. Company management has set a target of at least 650 oz of gold and 11,000 oz of silver. How many days should each mine be operated so that the target can be met at a minimum cost?
A) Saddle Mine: 1 days; Horseshoe Mine: 8 days; minimum cost $107,000
B) Saddle Mine: 4 days; Horseshoe Mine: 3 days; minimum cost $106,000
C) Saddle Mine: 1 days; Horseshoe Mine: 8 days; minimum cost $142,000
D) Saddle Mine: 8 days; Horseshoe Mine: 1 days; minimum cost $128,000
Correct Answer:

Verified
Correct Answer:
Verified
Q24: Formulate but do not solve the following
Q25: Find the graphical solution of the inequality.
Q26: Find the graphical solution of the inequality.
Q27: Find the optimal (maximum and minimum) values
Q28: A hunger-relief organization, has earmarked between $2
Q30: Determine graphically the solution set for the
Q31: Write a system of linear inequalities that
Q32: Find the optimal (maximum and/or minimum) value(s)
Q33: Kane Manufacturing has a division that produces
Q34: Write a system of linear inequalities that