A partially solved PERT problem is detailed in the table below.Times are given in weeks.
a.Calculate the expected time for each activity.Enter these values in the appropriate column in the table above.
b.Which activities form the critical path?
c.What is the estimated time of the critical path?
d.What are the project variance and the project standard deviation?
e.What is the probability of completion of the project after week 40?
Correct Answer:

Verified
(a)A=9.5 B=3 C=12 D=5.5 E=6 F=...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q2: Two critical path activities are candidates for
Q3: What was the name of the construction
Q5: Three critical path activities are candidates for
Q9: Pirmin's Bike Shop is behind on a
Q53: Define slack time.
Q82: Identify each of the purposes of project
Q88: If an activity whose normal duration is
Q91: Which of the following projects were completed
Q98: The project organization works best when which
Q129: _ is decreasing activity time in a