Multiple Choice
Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.
A) One; $400
B) One; $6,800
C) Two; $1,000
D) Two; $5,000
E) One or Two should be crashed; $1,400
Correct Answer:

Verified
Correct Answer:
Verified
Q3: What was the name of the construction
Q5: Three critical path activities are candidates for
Q7: A partially solved PERT problem is detailed
Q9: Pirmin's Bike Shop is behind on a
Q13: If an activity whose normal duration is
Q53: Define slack time.
Q82: Identify each of the purposes of project
Q88: If an activity whose normal duration is
Q91: Which of the following projects were completed
Q98: The project organization works best when which