Two Critical Path Activities Are Candidates for Crashing on a CPM

Question 2

Multiple Choice

Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost. Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.   A) One; $400 B) One; $6,800 C) Two; $1,000 D) Two; $5,000 E) One or Two should be crashed; $1,400


A) One; $400
B) One; $6,800
C) Two; $1,000
D) Two; $5,000
E) One or Two should be crashed; $1,400