Three Critical Path Activities Are Candidates for Crashing on a CPM

Question 5

Essay

Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.
Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.    a.What is the crash cost per unit time for each of the three activities? b.Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost? c.Which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost? a.What is the crash cost per unit time for each of the three activities?
b.Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost?
c.Which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost?

Correct Answer:

verifed

Verified

(a)crash cost X = $1,000 per d...